225-030 · Question #110
The Project Manager is responsible for all of the following EXCEPT:
The correct answer is D. selecting users for acceptance testing. See the full explanation below for the reasoning.
Question
The Project Manager is responsible for all of the following EXCEPT:
Options
- Aestimating task duration.
- Bcreating a work breakdown structure.
- Cmanaging scope.
- Dselecting users for acceptance testing.
How the community answered
(19 responses)- A5% (1)
- B21% (4)
- C5% (1)
- D68% (13)