225-030 · Question #110

The Project Manager is responsible for all of the following EXCEPT:

The correct answer is D. selecting users for acceptance testing. See the full explanation below for the reasoning.

Question

The Project Manager is responsible for all of the following EXCEPT:

Options

  • Aestimating task duration.
  • Bcreating a work breakdown structure.
  • Cmanaging scope.
  • Dselecting users for acceptance testing.

How the community answered

(19 responses)
  • A
    5% (1)
  • B
    21% (4)
  • C
    5% (1)
  • D
    68% (13)