Question
An office building lost power, and the generator started up. Users on several floors have reported their machines will not start, even though the generator is running. A technician works to divert power from other floors until all users are able to work. Which of the following is the BEST solution for the technician to recommend?
Options
- AAdd more redundancy to the power cabling
- BPurchase more battery backups for individual users
- CImplement desktop virtualization
- DIncrease the capacity of the backup generator
Unlock 220-1002 to see the answer