What is a component of the first stage of an application development CI/CD pipeline?

The correct answer is B. commitment and pushing of code into a version control system. In a CI/CD pipeline, the first stage begins when a developer commits and pushes code into a version control system (such as Git). This push event triggers all subsequent automated stages: the automated build phase compiles the code, and the automated testing phase runs tests…

Software Development and Design

Question

What is a component of the first stage of an application development CI/CD pipeline?

Options

  • Atriggering of the automated testing phase
  • Bcommitment and pushing of code into a version control system
  • Ctriggering of the automated build phase
  • Ddeveloper writing the initial lines of code

How the community answered

(18 responses)
  • A
    6% (1)
  • B
    89% (16)
  • D
    6% (1)

Explanation

In a CI/CD pipeline, the first stage begins when a developer commits and pushes code into a version control system (such as Git). This push event triggers all subsequent automated stages: the automated build phase compiles the code, and the automated testing phase runs tests against it. Writing code (option D) happens before the pipeline starts. Triggering build or testing phases (options A and C) occur in later stages, initiated by the commit.