Consider the following script: <?php echo date("M-d-Y", mktime(0, 0, 0, 12, 32, 1995)); ?> Zend 200-530 Exam What will be the output of the above script?

The correct answer is D. Jan-01-1996. See the full explanation below for the reasoning.

Question

Consider the following script: <?php echo date("M-d-Y", mktime(0, 0, 0, 12, 32, 1995)); ?> Zend 200-530 Exam What will be the output of the above script?

Options

  • AJan-01-1995
  • BFatal error
  • CDate out of range error
  • DJan-01-1996

How the community answered

(32 responses)
  • A
    3% (1)
  • B
    16% (5)
  • C
    9% (3)
  • D
    72% (23)