Multiple deportments In your company use a shared Oracle Cloud Infrastructure (OCI) tenancy to Implement their projects. You are in charge of managing the cost of OCI resources in the tenancy and…

The correct answer is A. Create a budget that matches your commitment amount and an alert at 100 percent of the forecast D. Set up different compartments for each department then track and analyze cost per compartment E. Set up a tag default that automatically applies tags to all specified resources created In a compartment then use these tags for cost analysis. Explanation/Reference: You can use budgets to track costs in your tenancy. After creating a budget for a compartment, you can set up alerts that will notify you if a budget is forecast to be exceeded or if spending surpasses a certain amount. OCI Cost Analysis -Visualization…

Design for Security

Question

Multiple deportments In your company use a shared Oracle Cloud Infrastructure (OCI) tenancy to Implement their projects. You are in charge of managing the cost of OCI resources in the tenancy and need to obtain better Insights Into department's usage. Which three options can you implement together to accomplish this?

Exhibit

1Z0-997 question #64 exhibit

Options

  • ACreate a budget that matches your commitment amount and an alert at 100 percent of the forecast
  • BUse the billing cost tracking report to analyze costs.
  • CSet up a consolidated budget tracking lags to analyze costs in ,1 granular manner
  • DSet up different compartments for each department then track and analyze cost per compartment
  • ESet up a tag default that automatically applies tags to all specified resources created In a compartment then use these tags for cost analysis.

How the community answered

(24 responses)
  • A
    75% (18)
  • B
    17% (4)
  • C
    8% (2)

Explanation

Explanation/Reference: You can use budgets to track costs in your tenancy. After creating a budget for a compartment, you can set up alerts that will notify you if a budget is forecast to be exceeded or if spending surpasses a certain amount. OCI Cost Analysis -Visualization tools Help understand spending patterns at a glance -Filter costs by Date, Tags and Compartments -Trend lines show how spending patterns are changing -To use Cost Analysis you must be a member of the Administrators group

Topics

#Cost management#Compartments#Resource tagging#Budget alerts