What is the difference between Prospective and Spend authorized suppliers?
The correct answer is D. Prospective suppliers are limited to sourcing and qualification activities, whereas Spend. See the full explanation below for the reasoning.
Question
What is the difference between Prospective and Spend authorized suppliers?
Options
- AProspective suppliers are suggested by internal users, whereas Spend authorized
- BProspective suppliers can participate in Sourcing activities only, whereas Spend
- CProspective suppliers are limited to purchase orders, whereas both purchase order and
- DProspective suppliers are limited to sourcing and qualification activities, whereas Spend
How the community answered
(43 responses)- A7% (3)
- B12% (5)
- C5% (2)
- D77% (33)