During an implementation where Procurement Contract and Supplier Portal are being implemented, the Procurement Contract user (buyer) has created deliverables on a supplier, which also has an…
The correct answer is B. The supplier can view the deliverable from the Supplier Portal under the Deliverables. See the full explanation below for the reasoning.
Question
During an implementation where Procurement Contract and Supplier Portal are being implemented, the Procurement Contract user (buyer) has created deliverables on a supplier, which also has an identified Supplier Portal user. The supplier has requested the buyer to email details of the deliverable. Advise the buyer on how he or she can communicate the deliverable details to the supplier through the application.
Options
- AThe supplier canview the deliverable from the Supplier Portal by clicking the Manage
- BThe supplier can view the deliverable from the Supplier Portal under the Deliverables
- CThe supplier can view the deliverable by opening the contract in the Contracts tab in the
- DThe supplier can view the deliverable by navigating to the Agreements tab from the
How the community answered
(27 responses)- A4% (1)
- B81% (22)
- C11% (3)
- D4% (1)