Oracle
1Z0-963 · Question #32
During a Procurement Contract implementation, a customer would like to set up their own line type for buying services. They intend to use this line for negotiating terms for future purchase of…
The correct answer is A. Item, buy. See the full explanation below for the reasoning.
Question
During a Procurement Contract implementation, a customer would like to set up their own line type for buying services. They intend to use this line for negotiating terms for future purchase of service and do not have a defined scope of work. Identify the source that the customer needs to select while creating the line type to meet this requirement.
Options
- AItem, buy
- CFree form, buy agreement
- DFree form, buy
How the community answered
(34 responses)- A79% (27)
- C12% (4)
- D9% (3)
Community Discussion
No community discussion yet for this question.