nerdexam
Oracle

1Z0-931-20 · Question #101

A customer wants to migrate to Autonomous Database (ADB) but only allows for a very small window of downtime. Golden Gate was advised to be used during the migration. For maximum reassurance of…

The correct answer is B. Only the migration to ADB is possible from an on-premise installation of Golden Gate. See the full explanation below for the reasoning.

Question

A customer wants to migrate to Autonomous Database (ADB) but only allows for a very small window of downtime. Golden Gate was advised to be used during the migration. For maximum reassurance of their end-users, the customer also would like to use Golden Gate as a fall-back scenario for the first 6 months after the migration. If customers complain, the on-premise data can be synchronised with the ADB Instance for a switch back. Which statement about the migration using Golden Gate is correct?

Options

  • AMigration to ADB is not possible using Golden Gate because the apply-process cannot be installed on
  • BOnly the migration to ADB is possible from an on-premise installation of Golden Gate.
  • CGolden Gate on premise is not certified with ADB because Golden Gate Cloud Service exists for this.
  • DThe fallback scenario is not possible using Golden Gate because the capture-process cannot be
  • EThe described scenario is correct, can be used for migration and fallback scenarios.

How the community answered

(43 responses)
  • A
    2% (1)
  • B
    79% (34)
  • C
    7% (3)
  • D
    9% (4)
  • E
    2% (1)

Community Discussion

No community discussion yet for this question.

Full 1Z0-931-20 Practice