Which action invokes supply chain orchestration and transfer of data to supply chain orchestration Interface tables?

The correct answer is C. running Min-Max Planning. Running Min-Max Planning is correct because it is a replenishment planning process that, when executed, evaluates inventory levels against defined minimum and maximum thresholds and - crucially - invokes Supply Chain Orchestration (SCO) by populating the SCO interface tables…

Implementing Business Logic Using CDI and Interceptors

Question

Which action invokes supply chain orchestration and transfer of data to supply chain orchestration Interface tables?

Options

  • Acreating Purchase Order Receipt
  • Brunning a scheduled process called "Create Transactions"
  • Crunning Min-Max Planning
  • Dcreating a new Inventory Organization for execution of supply chain orchestration

How the community answered

(20 responses)
  • A
    10% (2)
  • C
    85% (17)
  • D
    5% (1)

Explanation

Running Min-Max Planning is correct because it is a replenishment planning process that, when executed, evaluates inventory levels against defined minimum and maximum thresholds and - crucially - invokes Supply Chain Orchestration (SCO) by populating the SCO interface tables with the resulting supply requests (purchase orders, transfer orders, or work orders).

Why the distractors are wrong:

  • A (Purchase Order Receipt): This is a receiving transaction that records arrived goods; it does not trigger the orchestration planning engine or load the SCO interface tables.
  • B ("Create Transactions" scheduled process): This process is associated with cost accounting or inventory transaction processing - it moves data for costing purposes, not for supply chain orchestration invocation.
  • D (Creating a new Inventory Organization): This is a configuration/setup activity; it establishes a new org in the system but does not execute any orchestration or transfer planning data to interface tables.

Memory tip: Think "Min → Max → Move" - Min-Max Planning detects a supply gap, then moves that gap into the SCO interface tables so the orchestration engine can act on it. If inventory isn't being planned, it isn't being orchestrated.