1Z0-597 · Question #37

You are installing a SPARC T4 server at a customer site using a single-phase power feed. The power outlet is 15 meters (16.4 feet) from device. Which Enterprise Installation Standard (EIS) document…

The correct answer is D. Server operational checklist. See the full explanation below for the reasoning.

Question

You are installing a SPARC T4 server at a customer site using a single-phase power feed. The power outlet is 15 meters (16.4 feet) from device. Which Enterprise Installation Standard (EIS) document would you have highlighted this issue prior to installation?

Options

  • ASite audit report
  • BTest procedure plan
  • CPower routing map
  • DServer operational checklist

How the community answered

(38 responses)
  • A
    18% (7)
  • B
    3% (1)
  • C
    8% (3)
  • D
    71% (27)