Pre Deployment sign-off is a milestone for a OBIEE implementation and is based on successful completion of certain tasks. Which option is not one of them?
The correct answer is D. Project initiation and resourcing. See the full explanation below for the reasoning.
Question
Pre Deployment sign-off is a milestone for a OBIEE implementation and is based on successful completion of certain tasks. Which option is not one of them?
Options
- ATest Environment
- BSystem Testing
- CPerformance Tuning
- DProject initiation and resourcing
- EData Validation / Verification
How the community answered
(27 responses)- B4% (1)
- C19% (5)
- D70% (19)
- E7% (2)