In order to perform live migration on a virtual machine, which three prerequisites should be met?

The correct answer is C. The target server should have enough free space to run the VM. E. The source and target servers should be in same server pool. F. The target server should have access to the repository where the VM exist. See the full explanation below for the reasoning.

Question

In order to perform live migration on a virtual machine, which three prerequisites should be met?

Options

  • AVM exist in a clusterserver pool with high availability feature turned on.
  • BThe VM to be migrated has the high availability flag enabled.
  • CThe target server should have enough free space to run the VM.
  • DVM should be running or in pause state.
  • EThe source and target servers should be in same server pool.
  • FThe target server should have access to the repository where the VM exist.

How the community answered

(63 responses)
  • A
    13% (8)
  • B
    5% (3)
  • C
    79% (50)
  • D
    3% (2)