nerdexam
Oracle

1Z0-590 · Question #75

What two steps are required to ensure that virtual machines failover to a new server when their current server goes down?

The correct answer is A. Ensure that the Oracle VM Manager is always available by installing Oracle Clusterware. B. Turn on High Availability Mode in the server pool. In the question two steps are required so that you have to answer two here. Oracle Clusterware Ensure that your server is going to be restarted facility and it will provide you the failover feature for you as well. You have to turn on HA Mode in the server pool.

HA/DR and Migrations

Question

What two steps are required to ensure that virtual machines failover to a new server when their current server goes down?

Options

  • AEnsure that the Oracle VM Manager is always available by installing Oracle Clusterware.
  • BTurn on High Availability Mode in the server pool.
  • CAssign a virtual IP address to the server pool.
  • DTurn on HA in all virtual machines that will be restarted.
  • EEnsure all servers in the pool have identical CPU and memory.

How the community answered

(36 responses)
  • A
    83% (30)
  • C
    8% (3)
  • D
    3% (1)
  • E
    6% (2)

Explanation

In the question two steps are required so that you have to answer two here. Oracle Clusterware Ensure that your server is going to be restarted facility and it will provide you the failover feature for you as well. You have to turn on HA Mode in the server pool.

Topics

#high availability mode#VM failover#Oracle VM Manager#server pool HA

Community Discussion

No community discussion yet for this question.

Full 1Z0-590 Practice