1Z0-590 · Question #128

You are preparing for a scheduled outage of an Oracle VM server that host 4 VMs. You will provide with another server intent for live migration of the 4 virtual machines. Which four options apply to…

The correct answer is A. Only one VM at a time will be migrated. C. Add the new server to the existing server pool. D. Verify that both server involve in the live migration are identical (makes and model of hardware). G. Place the server (on which we schedule an outage) into maintenance mode to begin live migration. See the full explanation below for the reasoning.

Question

You are preparing for a scheduled outage of an Oracle VM server that host 4 VMs. You will provide with another server intent for live migration of the 4 virtual machines. Which four options apply to this procedure?

Options

  • AOnly one VM at a time will be migrated.
  • BPlace the new server into maintenance mode prior to begin migration.
  • CAdd the new server to the existing server pool.
  • DVerify that both server involve in the live migration are identical (makes and model of hardware).
  • EPublish the new IP addresses for all virtual machines following the migration.
  • FCreate a new server pool and preparation for the live migration.
  • GPlace the server (on which we schedule an outage) into maintenance mode to begin live migration.

How the community answered

(29 responses)
  • A
    83% (24)
  • B
    3% (1)
  • E
    3% (1)
  • F
    10% (3)

Community Discussion

No community discussion yet for this question.