What three statements are correct about task flow control flows?

The correct answer is A. A control flow would typically be initiated from a button or link that is being clicked. C. A Control flow can exist between a view activity and a method call. E. The name of a control flow must match the name of the view activity to which it navigates. See the full explanation below for the reasoning.

Question

What three statements are correct about task flow control flows?

Options

  • AA control flow would typically be initiated from a button or link that is being clicked.
  • BA view activity can be the source for many control flow rules.
  • CA Control flow can exist between a view activity and a method call.
  • DThe definition of control flows for a page are stored in the page backing bean.
  • EThe name of a control flow must match the name of the view activity to which it navigates.

How the community answered

(53 responses)
  • A
    85% (45)
  • B
    6% (3)
  • D
    9% (5)

Community Discussion