Which three statements are true with regard to I/O Resource plans?

The correct answer is A. You define inter-database resource plans with Database Resource Manager. B. You define Intra-database resource plans with Database Resource Manager. D. You enable a category plan with CellCLI. The Oracle Database Resource Manager (DBRM) has been enhanced for use with Exadata storage to manage user-defined intra and inter-database I/O resource usage to ensure customer defined SLAs are met.

Monitoring and Management

Question

Which three statements are true with regard to I/O Resource plans?

Exhibit

1Z0-536 question #27 exhibit

Options

  • AYou define inter-database resource plans with Database Resource Manager.
  • BYou define Intra-database resource plans with Database Resource Manager.
  • CYou define categories with Database Resource Manager.
  • DYou enable a category plan with CellCLI.

How the community answered

(43 responses)
  • A
    81% (35)
  • C
    19% (8)

Explanation

The Oracle Database Resource Manager (DBRM) has been enhanced for use with Exadata storage to manage user-defined intra and inter-database I/O resource usage to ensure customer defined SLAs are met.