The Hyperion Planning administrator needs to run several calculations in a specific order against two different databases within the application. Identify the two options that are not valid.

The correct answer is A. Esscmd D. MaxL. See the full explanation below for the reasoning.

Question

The Hyperion Planning administrator needs to run several calculations in a specific order against two different databases within the application. Identify the two options that are not valid.

Options

  • AEsscmd
  • BCalc Script
  • CBusiness Rule Sequence
  • DMaxL
  • EBusiness Rule Macro

How the community answered

(60 responses)
  • A
    82% (49)
  • B
    5% (3)
  • C
    3% (2)
  • E
    10% (6)