Which three components can be changed after the creation of the Planning application?

The correct answer is A. Number of years D. Initialization of WFP or CapEx Planning modules F. Year Dimension Name. See the full explanation below for the reasoning.

Question

Which three components can be changed after the creation of the Planning application?

Options

  • ANumber of years
  • BNames of plan types
  • CNumber of plan types
  • DInitialization of WFP or CapEx Planning modules
  • EWeekly distribution spread
  • FYear Dimension Name
  • GDefault Currency

How the community answered

(14 responses)
  • A
    71% (10)
  • C
    14% (2)
  • E
    7% (1)
  • G
    7% (1)

Community Discussion