Question
Your customer completes four production orders on a daily basis. One of the production orders has quality problems on some finished-good items. The requirements for this situation are:
Options
- AEnable lot control for the item. Store the lot in an isolated subinventory.
- BDefine the lot number as a rejected lot. Store this lot in an isolated subinventory.
- CCreate a reject locator. Move the items to this locator that prevents customer shipment.
- DEnable lot control for the item. Assign material status that disallows shipping transactions.
- EEnable serial control for the item. Store the serial control item in a separate subinventory that
- IIsolate the defective material from the regular production order
Unlock 1Z0-520 to see the answer
You've previewed enough free 1Z0-520 questions. Unlock 1Z0-520 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.