Oracle
1Z0-520 · Question #62
What are the three elements involved in submitting a concurrent request? (Choose three.)
The correct answer is C. providing completion option D. defining a submission schedule E. selecting the request or request set to be submitted. See the full explanation below for the reasoning.
Question
What are the three elements involved in submitting a concurrent request? (Choose three.)
Options
- Aselecting Operating Unit
- Bselecting report language
- Cproviding completion option
- Ddefining a submission schedule
- Eselecting the request or request set to be submitted
How the community answered
(34 responses)- A9% (3)
- B15% (5)
- C76% (26)
Community Discussion
No community discussion yet for this question.