Which three statements are true about the Move Order process? (Choose three.)

The correct answer is B. Replenishment and pick wave move orders are preapproved. D. If no planner is specified for the item, the requisition line is automatically approved. E. If no approvals are required in your organization, set the inventory organization parameters. See the full explanation below for the reasoning.

Question

Which three statements are true about the Move Order process? (Choose three.)

Options

  • ARequisition and pick release orders are preapproved.
  • BReplenishment and pick wave move orders are preapproved.
  • CRequisition and pick release orders are preapproved and require inspection.
  • DIf no planner is specified for the item, the requisition line is automatically approved.
  • EIf no approvals are required in your organization, set the inventory organization parameters

How the community answered

(38 responses)
  • A
    8% (3)
  • B
    71% (27)
  • C
    21% (8)

Community Discussion