Your customer has two manufacturing plants. The manufacturing process for both the plants is identical, but there are differences in specific areas. 1. Plant 1 uses min-max planning and Plant 2 uses…

The correct answer is B. Master Level: Stockable, Transactable, Build in WIP Organization Level: Inventory Planning C. Organization Level: Variable Lead Time, WIP Supply Subinventory. See the full explanation below for the reasoning.

Question

Your customer has two manufacturing plants. The manufacturing process for both the plants is identical, but there are differences in specific areas. 1. Plant 1 uses min-max planning and Plant 2 uses re-order point planning. 2. Plant 1 and Plant 2's Variable Lead Times are different. 3. Plant 1 and Plant 2 use two different WIP (Work In Process) supply subinventories. Which two attribute control settings meet the requirement? (Choose two.)

Options

  • AOrganization Level: WIP Supply Subinventory
  • BMaster Level: Stockable, Transactable, Build in WIP Organization Level: Inventory Planning
  • COrganization Level: Variable Lead Time, WIP Supply Subinventory
  • DMaster Level: Stockable, Variable Lead Time, Inventory Planning Method Organization Level:
  • EMaster Level: Transactable, Inventory Planning Method, Variable Lead Time
  • FMaster Level: WIP Supply Subinventory, Variable Lead Time, Stockable, Transactable, Build in

How the community answered

(37 responses)
  • A
    5% (2)
  • B
    84% (31)
  • D
    3% (1)
  • F
    8% (3)