1Z0-520 · Question #105
The client wants to implement reorder point planning for some items in the organization. They currently use min-max planning. What is the minimum amount of information that needs to be changed on…
The correct answer is C. Safety Stock Quantity, Inventory Planning Method set to Reorder Point, Forecast Quantity. See the full explanation below for the reasoning.
Question
The client wants to implement reorder point planning for some items in the organization. They currently use min-max planning. What is the minimum amount of information that needs to be changed on the items the client wants to plan?
Options
- ASafety Stock Quantity and Forecast
- BSafety Stock Quantity, Inventory Planning Method set to Reorder Point, Forecast Quantity,
- CSafety Stock Quantity, Inventory Planning Method set to Reorder Point, Forecast Quantity,
- DSafety Stock Quantity, Inventory Planning Method set to Reorder Point, Forecast Quantity,
- ESafety Stock Quantity, Inventory Planning Method set to Reorder Point, Forecast Quantity,
How the community answered
(54 responses)- A2% (1)
- B11% (6)
- C80% (43)
- D6% (3)
- E2% (1)