Oracle
1Z0-519 · Question #57
Production creates a move order requisition and specifies a subinventory as a source. This subinventory has insufficient quantity on-hand, but another subinventory has plenty available. What would…
The correct answer is D. Partial allocation for source subinventory is created. The balance of the requested quantity is not. See the full explanation below for the reasoning.
Question
Production creates a move order requisition and specifies a subinventory as a source. This subinventory has insufficient quantity on-hand, but another subinventory has plenty available. What would happen allocating the move order?
Options
- AAllocations would only be created in the subinventory where there is full available on-hand.
- BNothing. Without sufficient quantity in the source subinventory, allocation would not be created.
- CPartial allocation for source subinventory is created. The remaining requested quantity is canceled.
- DPartial allocation for source subinventory is created. The balance of the requested quantity is not
- EPartial allocation for source subinventory is created. The remaining allocation would be created in
How the community answered
(45 responses)- A4% (2)
- B2% (1)
- C9% (4)
- D82% (37)
- E2% (1)
Community Discussion
No community discussion yet for this question.