nerdexam
Oracle

1Z0-519 · Question #36

What are the three elements involved in submitting a concurrent request? (Choose three.)

The correct answer is C. providing completion option D. defining a submission schedule E. selecting the request or request set to be submitted. See the full explanation below for the reasoning.

Question

What are the three elements involved in submitting a concurrent request? (Choose three.)

Options

  • Aselecting Operating Unit
  • Bselecting report language
  • Cproviding completion option
  • Ddefining a submission schedule
  • Eselecting the request or request set to be submitted

How the community answered

(56 responses)
  • A
    7% (4)
  • B
    13% (7)
  • C
    80% (45)

Community Discussion

No community discussion yet for this question.

Full 1Z0-519 Practice