1Z0-518 · Question #29
What are the three elements involved in submitting a concurrent request? (Choose three.)
The correct answer is C. providing completion option D. defining a submission schedule E. selecting the request or request set to be submitted. Submitting a concurrent request in Oracle E-Business Suite revolves around three universal actions: choosing what to run (E), when to run it (D), and what to do when it finishes (C). These three elements appear on every submission form regardless of the request type, making…
Question
What are the three elements involved in submitting a concurrent request? (Choose three.)
Options
- Aselecting Operating Unit
- Bselecting report language
- Cproviding completion option
- Ddefining a submission schedule
- Eselecting the request or request set to be submitted
How the community answered
(25 responses)- A4% (1)
- B8% (2)
- C88% (22)
Explanation
Submitting a concurrent request in Oracle E-Business Suite revolves around three universal actions: choosing what to run (E), when to run it (D), and what to do when it finishes (C). These three elements appear on every submission form regardless of the request type, making them the core components of the submission process.
Why the distractors are wrong:
- A (Operating Unit) is part of your responsibility/context setup, not the submission form itself - it's set before you even open the request.
- B (Report language) may appear as a parameter for specific reports, but it is not a standard element present on all concurrent request submissions.
Memory tip: Think of the acronym "SWF" - Select the request, When to run it (schedule), Finish action (completion option). You always need to know what, when, and what happens after - everything else is optional or context-dependent.