Oracle
1Z0-516 · Question #749
Your manager has asked you to create a period close process that maximizes the efficiency of your two staff members and minimizes the number of closing days. Identify two sets of subledgers that can…
The correct answer is B. Order Management and Projects C. Payables and Receivables. See the full explanation below for the reasoning.
Question
Your manager has asked you to create a period close process that maximizes the efficiency of your two staff members and minimizes the number of closing days. Identify two sets of subledgers that can be closed concurrently. (Choose two.)
Options
- AProjects and Payables
- BOrder Management and Projects
- CPayables and Receivables
- DInventory and Receivables
- EPayables and Assets
How the community answered
(25 responses)- A8% (2)
- B72% (18)
- D16% (4)
- E4% (1)
Community Discussion
No community discussion yet for this question.