Oracle
1Z0-516 · Question #725
Purchasing has numerous activities that are performed as a key part of the Procure-to-Pay process. Select three activities that are performed in the Purchasing module that will integrate into…
The correct answer is B. performing receiving D. creating purchase orders E. creating purchase order detailed accounting information. See the full explanation below for the reasoning.
Question
Purchasing has numerous activities that are performed as a key part of the Procure-to-Pay process. Select three activities that are performed in the Purchasing module that will integrate into Payables. (Choose three.)
Options
- Acanceling invoices
- Bperforming receiving
- Cscheduling payments
- Dcreating purchase orders
- Ecreating purchase order detailed accounting information
How the community answered
(50 responses)- A12% (6)
- B84% (42)
- C4% (2)
Community Discussion
No community discussion yet for this question.