ABC Enterprise closes its books on March 31st. These activities have been identified to be performed for the closure of books. 1) post 2) translate 3) review 4) consolidate 5) revalue 6) run accounting reports 7) close accounting period In which order must these activities be performed?
Options
- A1, 3, 5, 2, 4, 6, 7
- B5, 2, 3, 1, 7, 4, 6
- C1, 5, 2, 3, 4, 7, 6
- D1, 3, 2, 5, 7, 4, 6