Oracle
1Z0-516 · Question #189
The GL accountant has defined the budget and wants the assistant accountants to enter and update the budget. The GL accountant wants this budget to be the default. What would be your response?
The correct answer is B. If the client wants to do this, the budget status must be current. See the full explanation below for the reasoning.
Question
The GL accountant has defined the budget and wants the assistant accountants to enter and update the budget. The GL accountant wants this budget to be the default. What would be your response?
Options
- AIf the client wants to do this, the budget status must be open.
- BIf the client wants to do this, the budget status must be current.
- CThe Oracle General Ledger budget functionality cannot satisfy this requirement.
- DIf the client wants to do this, customization of Oracle Workflow is the only option.
How the community answered
(40 responses)- A18% (7)
- B73% (29)
- C8% (3)
- D3% (1)
Community Discussion