Select the correct sequence of tasks required for period closing in Oracle General Ledger. 1. Verify that all journals are posted. 2. Close the period of each subledger. 3. Run the Trial Balance…

The correct answer is D. 6, 5, 2, 1, 3, 4. See the full explanation below for the reasoning.

Question

Select the correct sequence of tasks required for period closing in Oracle General Ledger. 1. Verify that all journals are posted. 2. Close the period of each subledger. 3. Run the Trial Balance report and other month-end reports. 4. Close the period and open the next period. 5. Perform reconciliation of subsidiary ledgers. 6. Transfer and import data from all subledgers.

Options

  • A6, 5, 2, 1, 4, 3
  • B3, 2, 1, 6, 4, 5
  • C6, 5, 1, 3, 2, 4
  • D6, 5, 2, 1, 3, 4
  • E6, 2, 3, 1, 5, 4

How the community answered

(38 responses)
  • B
    8% (3)
  • C
    5% (2)
  • D
    84% (32)
  • E
    3% (1)

Community Discussion

No community discussion yet for this question.

Full 1Z0-516 Practice