nerdexam
Oracle

1Z0-498 · Question #10

Project managers typically have the need to plan for granular labor resources, whereas only high- level planning is sufficient for financial purposes. Identify the two true statements about the…

The correct answer is A. You are allowed to create non-integrated resources manually in Primavera. B. When you import the project plan, all planning for non-integrated resources is summarized by. https://docs.oracle.com/cd/E51367_01/projectop_gs/OAPJF/F1121939AN17861.htm

Oracle Database Cloud Services Overview

Question

Project managers typically have the need to plan for granular labor resources, whereas only high- level planning is sufficient for financial purposes. Identify the two true statements about the Project Integration Gateway in this background.

Options

  • AYou are allowed to create non-integrated resources manually in Primavera.
  • BWhen you import the project plan, all planning for non-integrated resources is summarized by
  • CWhen you import the project plan, all planning for non-integrated resources is summarized by
  • DThe summary information does not become a resource class resource assignment in Oracle

How the community answered

(40 responses)
  • A
    85% (34)
  • C
    10% (4)
  • D
    5% (2)

Explanation

https://docs.oracle.com/cd/E51367_01/projectop_gs/OAPJF/F1121939AN17861.htm