Oracle
1Z0-498 · Question #10
Project managers typically have the need to plan for granular labor resources, whereas only high- level planning is sufficient for financial purposes. Identify the two true statements about the…
The correct answer is A. You are allowed to create non-integrated resources manually in Primavera. B. When you import the project plan, all planning for non-integrated resources is summarized by. https://docs.oracle.com/cd/E51367_01/projectop_gs/OAPJF/F1121939AN17861.htm
Oracle Database Cloud Services Overview
Question
Project managers typically have the need to plan for granular labor resources, whereas only high- level planning is sufficient for financial purposes. Identify the two true statements about the Project Integration Gateway in this background.
Options
- AYou are allowed to create non-integrated resources manually in Primavera.
- BWhen you import the project plan, all planning for non-integrated resources is summarized by
- CWhen you import the project plan, all planning for non-integrated resources is summarized by
- DThe summary information does not become a resource class resource assignment in Oracle
How the community answered
(40 responses)- A85% (34)
- C10% (4)
- D5% (2)
Explanation
https://docs.oracle.com/cd/E51367_01/projectop_gs/OAPJF/F1121939AN17861.htm
Topics
#Project Integration Gateway#Primavera#non-integrated resources#resource planning
Community Discussion
No community discussion yet for this question.