Oracle
1Z0-485 · Question #20
Identify the correct steps required to upgrade a 1/8th rack of Exadata to a 1/4th rack.
The correct answer is B. Activate all cores by using a software command. Not A: no need to remove doors. Not C: No additional Infiband Switch needed. Database Machine Upgrades Database Machine Components and Upgradeability
Installation and Configuration
Question
Identify the correct steps required to upgrade a 1/8th rack of Exadata to a 1/4th rack.
Exhibit
Options
- ARemove the doors of the 1/8th rack.
- BActivate all cores by using a software command.
- CRemove the doors of the 1/8th rack.
- DActivate all cores by using a software command.
How the community answered
(34 responses)- A3% (1)
- B74% (25)
- C6% (2)
- D18% (6)
Explanation
Not A: no need to remove doors. Not C: No additional Infiband Switch needed. * Database Machine Upgrades * Database Machine Components and Upgradeability
Topics
#rack upgrade#core activation#Exadata expansion#capacity scaling
Community Discussion
No community discussion yet for this question.
