You are designing a Load Plan in which you need to run Interfaces A and B one after the other while running Interface C at the same time. Which steps do you need to follow to achieve this?
The correct answer is A. Add a Parallel step, add two Serial steps underneath it, and then add A and B to one serial step. See the full explanation below for the reasoning.
Question
You are designing a Load Plan in which you need to run Interfaces A and B one after the other while running Interface C at the same time. Which steps do you need to follow to achieve this?
Options
- AAdd a Parallel step, add two Serial steps underneath it, and then add A and B to one serial step
- BAdd a Parallel step, drag A and B and C into the Parallel step
- CAdd aParallel step, add two Parallel steps underneath it, and then add A and B to one Parallel
- DAdd a Parallel step, add three serial steps underneath it, and then add A to the first Serial step, to
How the community answered
(39 responses)- A82% (32)
- B5% (2)
- C10% (4)
- D3% (1)