You are designing a Load Plan in which you need to run Interfaces A and B one after the other while running Interface C at the same time. Which steps do you need to follow to achieve this?

The correct answer is A. Add a Parallel step, add two Serial steps underneath it, and then add A and B to one serial step. See the full explanation below for the reasoning.

Question

You are designing a Load Plan in which you need to run Interfaces A and B one after the other while running Interface C at the same time. Which steps do you need to follow to achieve this?

Options

  • AAdd a Parallel step, add two Serial steps underneath it, and then add A and B to one serial step
  • BAdd a Parallel step, drag A and B and C into the Parallel step
  • CAdd aParallel step, add two Parallel steps underneath it, and then add A and B to one Parallel
  • DAdd a Parallel step, add three serial steps underneath it, and then add A to the first Serial step, to

How the community answered

(39 responses)
  • A
    82% (32)
  • B
    5% (2)
  • C
    10% (4)
  • D
    3% (1)