1Z0-481 · Question #68
You have configured and added the extract and Replicate tasks using the direct load method what do you need to do to get the processes up and running?
The correct answer is A. Start the Extract task. In reference guide, page 279, "Use the RMTTASK parameter for an initial-load Extract to initiate a Replicat processing task during a GoldenGate direct load or a direct bulk load to SQL*Loader. RMTTASK directs Extract to communicate directly with Replicat over TCP/IP and…
Question
You have configured and added the extract and Replicate tasks using the direct load method what do you need to do to get the processes up and running?
Options
- AStart the Extract task.
- BStart the Extract task and then start the Replicat task.
- CStart the Extract task; wait for it to stop and than start the Replicate task.
- DStart the Replicate task
How the community answered
(27 responses)- A81% (22)
- B11% (3)
- C4% (1)
- D4% (1)
Explanation
In reference guide, page 279, "Use the RMTTASK parameter for an initial-load Extract to initiate a Replicat processing task during a GoldenGate direct load or a direct bulk load to SQL*Loader. RMTTASK directs Extract to communicate directly with Replicat over TCP/IP and bypasses the use of aCollector process or disk storage. RMTTASK also directs Extract to request that Managerstart Replicat automatically, and then stop Replicat when the run is finished. "