1Z0-466 · Question #23
Select the three statements that are true about the OUM Manage focus area.
The correct answer is D. It is appropriate for managing all types of Oracle Consulting engagements. E. It is used to gather requirements and analyze, design, build, and test custom software. F. It provides a framework for development of services that supports enterprise or strategic-level interactions. Project management enables the project manager to manage delivery of an agreed upon level of solution quality while planning for and controlling the scope, cost, and schedule. The Manage focus area has three phases: - Project Start Up Phase - Project Execution and Control Phase…
Question
Select the three statements that are true about the OUM Manage focus area.
Options
- AIt is aligned with the Project management Institute's Project management Body of Knowledge (PMBOK).
- BIt is Oracle's standard is on configuration of applications.
- CIts main focus is on configuration of applications.
- DIt is appropriate for managing all types of Oracle Consulting engagements.
- EIt is used to gather requirements and analyze, design, build, and test custom software.
- FIt provides a framework for development of services that supports enterprise or strategic-level interactions.
How the community answered
(40 responses)- A5% (2)
- B3% (1)
- C10% (4)
- D83% (33)
Explanation
Project management enables the project manager to manage delivery of an agreed upon level of solution quality while planning for and controlling the scope, cost, and schedule. The Manage focus area has three phases: - Project Start Up Phase - Project Execution and Control Phase - Project Closure Phase