1Z0-466 · Question #1
At the end of iteration phase, during Project Execution and Control, which three key tasks should be conducted?
The correct answer is A. QM.050 Perform Quality Assurance B. WM.050 Manage Approvals C. CMM.030 Manage Project Team Communication. Not D: Belongs to project start up- Not E: Belongs to project closure. Not F: Belongs to project closure. Not G: Belongs to project closure.
Oracle Linux Concepts
Question
At the end of iteration phase, during Project Execution and Control, which three key tasks should be conducted?
Exhibit
Options
- AQM.050 Perform Quality Assurance
- BWM.050 Manage Approvals
- CCMM.030 Manage Project Team Communication
- DPKM.020 Conduct Baseline Risk Assessment
- ESM.060 Close Scope management
- FPKM.060 Conduct Post-Production Risk Assessment
- GOCHM.040 Establish Follow-Up process
How the community answered
(21 responses)- A81% (17)
- D5% (1)
- E5% (1)
- F10% (2)
Explanation
Not D: Belongs to project start up- Not E: Belongs to project closure. Not F: Belongs to project closure. Not G: Belongs to project closure.
Topics
#OUM#project execution#iteration phase#quality assurance