You must ensure that your Mappings do not run into connectivity issues when moving data from server A to server B by using an AGT agent that is running on server B. How must you test this by using…

The correct answer is B. In Topology, test the connections to servers A and B by using the AGT agent. this link even choice A is right as its alternative/additional method for testing connectivity

Setting Up ODI Components

Question

You must ensure that your Mappings do not run into connectivity issues when moving data from server A to server B by using an AGT agent that is running on server B. How must you test this by using ODI Studio running on machine C? (Choose the best answer.)

Options

  • AUse OdiPingAgent in a package to ping AGT agent.
  • BIn Topology, test the connections to servers A and B by using the AGT agent.
  • CIn Topology, test the connections to the AGT agent.
  • DIn Topology, test the connections to servers A and B by using Local (No Agent).

How the community answered

(41 responses)
  • A
    2% (1)
  • B
    83% (34)
  • C
    10% (4)
  • D
    5% (2)

Explanation

this link even choice A is right as its alternative/additional method for testing connectivity

Topics

#topology#connectivity testing#AGT agent#data server connections