Which two case elements can have due dates configured? (Choose two.)
The correct answer is A. Case B. Case data. See the full explanation below for the reasoning.
Question
Which two case elements can have due dates configured? (Choose two.)
Options
- ACase
- BCase data
- CEvents
- DMilestones
- EActivities
How the community answered
(45 responses)- A84% (38)
- C9% (4)
- D4% (2)
- E2% (1)