Which statement is true for a BPMN subprocesses?

The correct answer is C. The subprocess can be reused and called from other processes. See the full explanation below for the reasoning.

Question

Which statement is true for a BPMN subprocesses?

Options

  • AIt has access to the data variables of the main process.
  • BData have to be explicitlypassed back and forth between the main process and the subprocess.
  • CThe subprocess can be reused and called from other processes.
  • DThe sequence flow inside a subprocess can be diverted and joined to the main flow without going

How the community answered

(47 responses)
  • A
    4% (2)
  • B
    9% (4)
  • C
    72% (34)
  • D
    15% (7)