Which two statements are true about working with tasks in Business Process Workspace?

The correct answer is A. A user can create personal to-do tasks that are unassociated with a process instance. D. You can display the process model and view the path a process instance has taken. See the full explanation below for the reasoning.

Question

Which two statements are true about working with tasks in Business Process Workspace?

Options

  • AA user can create personal to-do tasks that are unassociated with a process instance.
  • BDelegating a task means to transfer the task to another user or group.
  • CYou can see how long each completed step has taken to finish.
  • DYou can display the process model and view the path a process instance has taken.

How the community answered

(29 responses)
  • A
    72% (21)
  • B
    7% (2)
  • C
    21% (6)