Your manager has tasked you with planning an Oracle Grid Infrastructure 12cR1 installation. Which three actions must be performed before beginning the installation?
The correct answer is A. All nodes are configured with the same operating system and version. B. Network interfaces are configured for public and private traffic. D. Shared storage is available from all servers. https://docs.oracle.com/database/121/CWLIN/chklist.htm#CWLIN454
Installing and Configuring Oracle Grid Infrastructure for a Cluster
Question
Your manager has tasked you with planning an Oracle Grid Infrastructure 12cR1 installation. Which three actions must be performed before beginning the installation?
Options
- AAll nodes are configured with the same operating system and version.
- BNetwork interfaces are configured for public and private traffic.
- CA valid voting disk file is available on at least one node.
- DShared storage is available from all servers.
- EEach public network interface has its own subnet
How the community answered
(28 responses)- A79% (22)
- C14% (4)
- E7% (2)
Explanation
https://docs.oracle.com/database/121/CWLIN/chklist.htm#CWLIN454
Topics
#pre-installation requirements#shared storage#OS configuration#network interfaces