When creating a bounded task flow that uses ADF Business Components, which two steps do you need to perform to enable the task flow to manage its own transaction"? (Choose two.)
The correct answer is A. Define transaction properties at the task-flow level D. Define task flow return activities in the flow and associate "End transaction" attribute values with. See the full explanation below for the reasoning.
Question
When creating a bounded task flow that uses ADF Business Components, which two steps do you need to perform to enable the task flow to manage its own transaction"? (Choose two.)
Options
- ADefine transaction properties at the task-flow level
- BInclude a phaseUstener in a managed bean with methods for commit and rollback
- CAdd the application module commit and rollback operations as buttons or links on the last JSF
- DDefine task flow return activities in the flow and associate "End transaction" attribute values with
How the community answered
(52 responses)- A83% (43)
- B8% (4)
- C10% (5)