Oracle
1Z0-338 · Question #24
Which two steps are needed to set up instance caging on an Exadata system? (Choose two.)
The correct answer is A. Set the CPU_COUNT parameter to the maximum number of CPUs that the database instance should B. Enable a resource plan to manage the CPUs. Explanation/Reference:
Security and Data Management
Question
Which two steps are needed to set up instance caging on an Exadata system? (Choose two.)
Options
- ASet the CPU_COUNT parameter to the maximum number of CPUs that the database instance should
- BEnable a resource plan to manage the CPUs.
- CSpecify the optimization objective as low_latency or high__throughput.
- DSet PGA_AGGREGATE_LIMIT to an acceptable level for the intended instances.
- EChange the initialization parameter THREADED_EXECUTION to TRUE and restart the instance.
How the community answered
(27 responses)- A78% (21)
- C7% (2)
- D4% (1)
- E11% (3)
Explanation
Explanation/Reference:
Topics
#instance caging#CPU_COUNT#resource plan#CPU management