Oracle
1Z0-330 · Question #149
While creating a compensation plan, the compensation manager of your client's organization chooses to enable Compensation Change statement. As an implementation consultant, which is the dependent…
The correct answer is C. Enable components and create a component linked to the budget pool (Configure Compensation. https://docs.oracle.com/cd/E37583_01/doc.1116/e22776/F387136AN11E5B.htm
Compensation Plan Configuration
Question
While creating a compensation plan, the compensation manager of your client's organization chooses to enable Compensation Change statement. As an implementation consultant, which is the dependent configuration that you would advise the compensation manager to perform? (Choose the best answer.)
Options
- AEnable components and create at least one component (Configure Compensation Components).
- BEnable the Communications tab type (Configure Worksheet Page Layout).
- CEnable components and create a component linked to the budget pool (Configure Compensation
- DConfigure related components (Configure Worksheet Page Layout: Detail Table tab.)
How the community answered
(52 responses)- A6% (3)
- B4% (2)
- C77% (40)
- D13% (7)
Explanation
https://docs.oracle.com/cd/E37583_01/doc.1116/e22776/F387136AN11E5B.htm
Topics
#compensation change statement#budget pool#dependent configuration#compensation components