Your Workforce Compensation Plan has the following Plan Cycle setup: - Evaluation Period Start Date: 1-Jan-2014 - Evaluation Period End Date: 31-Dec-2014 - Worksheet Update Period Start Date…
The correct answer is A. Schedule the Refresh Workforce Compensation Data process nightly to ensure that line. See the full explanation below for the reasoning.
Question
Your Workforce Compensation Plan has the following Plan Cycle setup:
- Evaluation Period Start Date: 1-Jan-2014
- Evaluation Period End Date: 31-Dec-2014
- Worksheet Update Period Start Date: 1-Jan-2014
- Worksheet Update Period End Date: 31-Dec-2014
- HR Data Extraction: 31-Dec-2014
- Eligibility Determination Date: 31-Dec-2014
- Worksheet Update Period Start Date: 1-Nov-2014
- Worksheet Update Period End Date: 31-Jan-2015
Due to reorganization in the month of December 2014, the Marketing department was split into two new departments: Branding and Communications, which resulted in transfers of many employees from one manager to another. You, as the compensation administrator, are required to ensure that all the relevant organizational changes are included in the Compensation Worksheet. What would you have to do to accomplish this? (Choose the best answer.)
Options
- ASchedule the Refresh Workforce Compensation Data process nightly to ensure that line
- BRun the Refresh Workforce Compensation Data process on 1-Nov-2014 because that is the date
- CValidate Plan Setup to ensure that all HR Data updates are accounted in the worksheet.
- DRun the Back Out Workforce Compensation Data process with the "Full back out"option.
How the community answered
(56 responses)- A84% (47)
- B2% (1)
- C4% (2)
- D11% (6)
Community Discussion
No community discussion yet for this question.