Which three dates are mandatory while creating plan cycles? (Choose three.)
The correct answer is A. Evaluation Period Start Date B. Worksheet Update Period Start Date C. Plan Access Start Date. See the full explanation below for the reasoning.
Question
Which three dates are mandatory while creating plan cycles? (Choose three.)
Options
- AEvaluation Period Start Date
- BWorksheet Update Period Start Date
- CPlan Access Start Date
- DHR Data Extraction Date
- EPerformance Rating Date
- FDefault Due Date
How the community answered
(43 responses)- A79% (34)
- D12% (5)
- E7% (3)
- F2% (1)