After Go-Live, your customer decides to change the application flow pages so that they are presented in a different order, and also to include additional pages. The system does not allow them to…
The correct answer is B. that the application flow actions are associated with the correct page C. that a Thank You page is included and is the last page in the flow. See the full explanation below for the reasoning.
Question
After Go-Live, your customer decides to change the application flow pages so that they are presented in a different order, and also to include additional pages. The system does not allow them to save the new configuration. What two things should you ensure to troubleshoot this? (Choose two.)
Options
- Athat the names of the pages are not misspelled
- Bthat the application flow actions are associated with the correct page
- Cthat a Thank You page is included and is the last page in the flow
- Dthat there are not too many pages
- Ethat there are enough pages
How the community answered
(65 responses)- A3% (2)
- B83% (54)
- D9% (6)
- E5% (3)