Consider a situation where a worker failed with a core dump and cannot be restarted. Although the worker is listed as running in the adctrl utility, there is no operating system-level process for…
The correct answer is B. 4, 3, 1, 2. See the full explanation below for the reasoning.
Question
Consider a situation where a worker failed with a core dump and cannot be restarted. Although the worker is listed as running in the adctrl utility, there is no operating system-level process for the erring worker. In this situation, the only option is to restart the patch. What are the steps performed to restart the patch? 1. Tell the manager that a worker acknowledges quit. 2. Restart the patch. 3. Tell the manager that a worker failed its job. 4. Tell the worker to shut down or quit (all workers). Identify the correct sequence in which you perform the task in the above scenario.
Options
- A1, 3, 4, 2
- B4, 3, 1, 2
- C4, 1, 3, 2
- D1, 3, 2, 4
- E3, 4, 1, 2
How the community answered
(40 responses)- A8% (3)
- B78% (31)
- C3% (1)
- D10% (4)
- E3% (1)